Project Snapshot
Active Ticket Matrix
Item | Status | Assigned to | Pending Actions | Vertic Approved | Client Approved | Due Date | Knowledge Base Link |
---|---|---|---|---|---|---|---|
done | @Harry Mycock @Tim Sweeney | Vertic to reconcile against testing |
|
|
|
| |
in progress | Vertic | @Harry Mycock Create data model based on Flow logic fields @iSantana Baskar (Unlicensed) to review tickets in client review |
|
|
|
| |
not started | Concept Care | @iSantana Baskar (Unlicensed) @Dean Jones (Unlicensed) to provide case rules and requirements |
|
|
|
| |
not started | Concept Care | @iSantana Baskar (Unlicensed) @Dean Jones (Unlicensed) to provide care plan example from Flow Logic |
|
|
|
| |
in progress | Vertic | @Harry Mycock Create page layouts based on Flow Logic |
|
|
|
| |
in progress | Concept Care | @iSantana Baskar (Unlicensed) / @Dean Jones (Unlicensed) to provide profile access to Apps on ticket |
|
| Oct 26, 2023 |
| |
in progress | Concept Care | @iSantana Baskar (Unlicensed) @Dean Jones (Unlicensed) - we are still awaiting this information from HR |
|
| Oct 26, 2023 |
| |
Client REVIEW | Concept Care |
|
|
| Oct 26, 2023 |
| |
not started | Concept Care | @iSantana Baskar (Unlicensed) / @Dean Jones (Unlicensed) to provide on ticket |
|
| Oct 26, 2023 |
| |
in progress | Vertic | Profiles have been created and access attributes will be assigned pre-go-live |
|
| Dec 20, 2023 |
| |
in progress | Concept Care | @iSantana Baskar (Unlicensed) to review requirements |
|
|
|
| |
Vertic to Complete UAT Component/Automation Testing - https://verticconsulting.atlassian.net/browse/CCS-21 | in progress | Vertic |
|
|
| Nov 14, 2023 |
|
Vertic to provide video demos of User Stories | in progress | Vertic |
|
|
| Nov 14, 2023 |
|
Concept Care to provide first round of feedback |
| Concept Care |
|
|
|
|
|
On site workshop TBC |
|
|
|
|
|
|
|
Deployment of components to Production | not started | Vertic |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Risk Management:
Risk | Action | Assigned to |
---|---|---|
Santana away through October meant a pause on requirements |
|
|
Santana Away from 1st November - 20th November |
|
|
9th Weekly workshop client no show |
|
|
16th Weekly workshop client no show |
|
|
2 month lead time required after initial Flow Logioc database export before go-live can happen |
|
|
No Conga sign license in place as of January 1o |
|
|
Blockers
Blocker | Action | Assigned to |
---|---|---|
|
|
|
|
|
|
Key DatesTimeline
Epic | Description | Sandbox Date | Production Date |
---|---|---|---|
|
|
|
|